Riverside Water Treatment Plant Expansion
Riverside Regional Water Authority · Riverside, USA · Design-Build — Water/Wastewater · Active — Month 5 of 18
$12,200,000
Contract Value
5/18
Months Complete
27%
Overall Progress
JE
Jordan Ellis
Project Manager
MR
Morgan Reyes
Senior Estimator
PN
Pat Nguyen
Owner's Rep
CB
Casey Brooks
Superintendent
Construction Copilot
4 Alerts
Process Equipment 8.9% Over Budget
Filter vessels + chemical feed system now $285K over budget. SS surcharge and media design change driving variance. Electrical/I&C also $180K over.
Review Budget
RFI-007 Blocking Critical Path
Pipe routing conflict at Grid C-4 unresolved for 51 days. MEP sub cannot order pipe sleeves. Process piping and equipment install are blocked.
Open RFI-007
Steel Erection 9 Days Behind
Filter building structural steel is 55% complete but should be done. Crane availability and bolt inspection backlog. Critical path impact.
View Schedule
Filter Delivery Delayed 8 Weeks
Dual-media filter vessels now arriving Sep 14 — 8 weeks late. Commissioning start pushed to December. Cascading impact on project completion.
View Risk Log
Earned Value (EVM) Month 7 Snapshot
0.89
CPI (Cost Perf.)
Under 1.0 = over budget
0.87
SPI (Schedule Perf.)
Under 1.0 = behind schedule
$13,707,865
EAC (Est. at Complete)
Forecast final cost
-$1,507,865
VAC (Variance at Complete)
Budget overrun forecast
Progress (27%) 5 of 18 months
Active Tasks 2 Overdue
Structural Steel — Filter Building
Structure · Due Jun 4
Overdue
CB
RFI-007 Resolution — Pipe Routing
MEP · Due Apr 29
Overdue
JE
Chemical Building Masonry
Structure · Due Jun 28
In Progress
CB
BABA Certification Package
Compliance · Due Jul 10
Todo
MR
EPA SRF Progress Report (Jul 15)
Compliance · Due Jul 15
Todo
JE
Filter Vessel Shop Drawing Review
Submittals · Due Jun 20
In Progress
MR
RFI Log 2 Open
RFI-007
DI pipe header conflicts with structural beam at Grid C-4
Issued
51d open
RFI-008
Filter backwash pump base elevation — drawing vs. shop dwg
Issued
45d open
RFI-009
Chemical storage room ventilation — OSHA vs. spec conflict
Issued
38d open
RFI-015
Blower pad dimensions — manufacturer changed base footprint
Issued
14d open
RFI-004
Concrete mix design for submerged basin walls
Responded
RFI-001
Filter vessel anchor bolt layout vs. basin slab embedment
Responded
CPM Schedule 14 Days Behind Critical Path
Site Mobilization & Earthwork ● CRITICAL
Jan 5 → Mar 15
Concrete — Basins & Footings ● CRITICAL
Feb 16 → May 1
Structural Steel — Filter Building ● CRITICAL
Apr 29 → Jun 14
Building Envelope ● CRITICAL
Jun 21 → Aug 1
Process Equipment Delivery & Install ● CRITICAL
Sep 14 → Oct 9
MEP / Electrical / I&C
Jul 27 → Dec 11
7d float
Process Piping ● CRITICAL
Aug 1 → Sep 28
SCADA / Instrumentation & Controls ● CRITICAL
Oct 14 → Dec 7
Commissioning & Startup ● CRITICAL
Dec 7 → Jul 4
Budget vs. Actual by CSI Division $223K MEP Overrun
CSI
Division
Budget
Actual
Variance
01
General Requirements
$320,000
$318,500
$1,500
02
Sitework
$650,000
$598,400
$51,600
03
Concrete
$980,000
$901,200
$78,800
05
Structural Steel
$720,000
$392,500
+$8,000 over
11
Process Equipment
$3,200,000
$185,000
+$285,000 over
13
Process Piping
$1,120,000
15
Mechanical (HVAC)
$850,000
16
Electrical & I&C / SCADA
$2,400,000

This is a live demo. Your projects will look exactly like this.

Caelum Build catches budget overruns, schedule slips, and missing documents — before they cost you money.
Start your 7-day free trial today. No credit card required to explore.

C
Ask the Project
Southgate Office Building
0 / 10 questions used
Ask any question about the Southgate project — drawings, specs, budget, schedule, or RFIs.